Modernization of the entire production area for ointments, gels, and suppositories, GFA 1,700 m²
Preparation of extended design planning for the modernization of the entire production facility as well as the turnkey implementation of the following trades:
- technical building services
- cleanroom interior fit-out
Project Timeframe
Planning 11/17-04/18
Implementation 08/18-12/18